Under Florida’s construction lien law, suppliers and subcontractors who aren’t paid can place a lien on your property, even if you paid your contractor. You protect yourself by tracking notices, collecting lien releases and getting a final payment affidavit before you make the last payment.

The rules, in brief

See also:Contact →
RuleWhat the statute says
Notice to Owner deadlineSuppliers and subcontractors without a direct contract with you must serve it before they start, or no later than 45 days after they start furnishing labor or materials (s. 713.06(2)(a))
Payments are protectedYou owe nothing to a lienor, other than laborers, who had not sent a Notice to Owner when you made a payment (s. 713.06(3)(c))
Final payment affidavitYou can hold the final payment until the contractor provides it. It lists any lienor not paid in full and the amount due (s. 713.06(3)(d))
Notice of CommencementRequired when the job value is over $5,000

The documents to know

Closeout documents included
Final payment affidavit and releases delivered with your job file.
Talk to our team
DocumentWhat it isWhat to do
Notice of CommencementRecorded notice that the job has started, required over $5,000Record it and post a copy on site
Notice to OwnerSent by suppliers/subs who may have lien rightsKeep every one you receive
Lien release (waiver)Confirms a party has been paidCollect one from each Notice-to-Owner sender
Final payment affidavitContractor states who has and hasn’t been paidGet it before final payment
Lien law disclosureRequired in any direct residential contract over $2,500 for a 1 to 4 unit home (s. 713.015). Printed in at least 12-point, all-caps, bold type, on the front page or a separate pageRead it, then sign and date it
Recovery Fund noticeRequired notice in residential contractsRead it. It explains your rights
Before the final payment: affidavit and releases in hand.
Before the final payment: affidavit and releases in hand.

Before your final payment

  1. List every Notice to Owner you received
  2. Match each one to a signed release
  3. Get the contractor’s final payment affidavit
  4. Then make the final payment

We provide the final payment affidavit and releases at closeout, as part of the job file.

Why a lien can happen even if you paid

Florida gives suppliers and subcontractors lien rights so they get paid for materials and labor that improve your property. If your contractor doesn’t pay them, they can pursue a lien against the property. That is why collecting releases matters.

Keep a simple file

  • A copy of the recorded Notice of Commencement
  • Every Notice to Owner you receive, with the date
  • Each payment you make, with proof
  • Each lien release you collect
  • The final payment affidavit

When to ask for help

If you receive a notice from a supplier you don’t recognize, ask your contractor about it right away. For legal questions, talk to a Florida attorney. This article is general information, not legal advice.

Frequently asked questions

What is a Notice to Owner in Florida?

A notice from a supplier or subcontractor letting you know they are working on your project and may have lien rights. It must be served before they start, or within 45 days after they start furnishing labor or materials.

What is a lien release?

A signed document confirming a party has been paid and waives lien rights for that payment.

Do I need a Notice of Commencement for a roof?

Yes, when the job value is over $5,000. The 2023 law raised the threshold from $2,500.

Can I hold the final payment?

Yes. You can hold the final payment until the contractor gives you the final payment affidavit (s. 713.06(3)(d)).

Does SafeTech provide releases?

Yes, at closeout with the final payment affidavit.

About the author

Roshy Rajan has worked in Broward County real estate and construction since 2006. He founded SafeTech Roofing and Windows (SafeTech Builders Inc.) after a hurricane left a friend with roof and window damage and the referrals kept coming. Florida Certified General Contractor CGC1537934 · Certified Roofing Contractor CCC1336954 · BBB Accredited.

Licensed and insured. Florida CGC1537934 · CCC1336954.

Closeout documents included

Final payment affidavit and releases delivered with your job file.

Talk to our team Call (954) 665-3231